Procurement Act 2023 notices: a guide for councils

The notices a council in England publishes on the Central Digital Platform under the Procurement Act 2023, from planning a procurement to paying under the contract and ending it.

By the PactTax team. Last reviewed .

The Act and the platform

The Procurement Act 2023 came into force on 24 February 2025. Notices are published on the Central Digital Platform, which the Cabinet Office describes as an enhanced version of Find a Tender. An amount payable under a contract includes VAT (section 123(2)).

Notices through a contract's life

Procurement Act 2023 notices
NoticeWhen
Pipeline notice (section 93)Where the council considers it will pay more than £100 million under relevant contracts in the coming financial year: within 56 days beginning with the first day of that year, covering public contracts over £2 million for which it intends to publish a tender or transparency notice in the 18 months beginning that day.
Preliminary market engagement notice (section 17)Before the tender notice, where the council carried out preliminary market engagement, or reasons in the tender notice for not publishing one.
Planned procurement notice (section 15)Optional. Published at least 40 days and no more than 12 months before the tender notice, it can allow shorter tendering periods.
Tender notice (section 21)To begin a competitive tendering procedure.
Transparency notice (section 44)Before a direct award under section 41 or 43.
Contract award notice (section 50)Before entering into the contract. The standstill period is eight working days beginning with the day it is published, with some exceptions (section 51).
Contract details notice (section 53)Within 30 days beginning with the day the contract is entered into, or 120 days for a light touch contract. Over £5 million, a copy of the contract within 90 days, or 180 days for light touch.
Key performance indicators (sections 52 and 71)Over £5 million, at least three set before the contract is entered into and published. Performance against them is assessed and published at least once every 12 months and on termination.
Contract change notice (section 75)Before modifying the contract, unless the change is one the Act exempts.
Contract termination notice (section 80)Within 30 days beginning with the day the contract is terminated.

Section 71's performance publication came into force on 1 January 2026, for public contracts awarded under the Act.

Payments compliance notices (section 69)

For each reporting period in which it made a payment, or a sum became payable, under a public contract, a council publishes a payments compliance notice within 30 days beginning with the last day of the period. Reporting periods end on 31 March and 30 September. For English councils section 69 came into force on 1 January 2026, for public contracts awarded under the Act. The notice gives (regulation 38):

  • The dates of the first and last days of the reporting period.
  • The average number of days taken to pay, counting from the day after the invoice was received.
  • The percentage of payments made within 30 days, within 31 to 60 days, and on day 61 or later.
  • The proportion of invoices paid within the 30-day term section 68(2) implies into every public contract.
  • The percentage of sums that became payable in the period but were not paid within it.
  • A statement by the director or similar officer responsible for the council's finances approving the notice, with their name and job title.

A payment counts as made when the supplier receives it. The Cabinet Office's guidance says grant payments are not caught.

Payments over £30,000 (section 70)

From 1 April 2026, a council publishes information about each payment of more than £30,000 it makes under a public contract, within 30 days beginning with the last day of the quarter in which it was made. Quarters end on 31 March, 30 June, 30 September and 31 December. Regulation 38A sets the information: the council's name, address and identifier, the procurement and contract identifiers, the supplier's name and identifier, the value of the payment net of VAT and the date it was made. The Cabinet Office's guidance says the £30,000 test includes VAT, that the duty covers contracts whose procurement began on or after 1 April 2026, and that the first publication was due by 29 July 2026. It does not replace the Transparency Code.

Below-threshold contracts

For a council, a below-threshold contract is notifiable when its estimated value is £30,000 or more (section 87(4)). The council publishes a below-threshold tender notice before advertising it, unless it invites only particular suppliers, and a contract details notice as soon as reasonably practicable after entering into it (section 87).

Thresholds from 1 January 2026

Schedule 1 thresholds for a council, including VAT
ContractThreshold
Goods, services or works: sub-central authority£207,720
Works£5,193,000
Light touch contracts£663,540
Concessions£5,193,000
Light touch concessions£5,372,609

These apply from 1 January 2026 to procurements begun on or after that day (the Procurement Act 2023 (Threshold Amounts) (Amendment) Regulations 2025), and the Cabinet Office's guidance gives them for 1 January 2026 to 31 December 2027. Procurement regulated by the Welsh Ministers is outside those regulations.

How PactTax helps

In PactTax for councils, the payments compliance notice for each half year is worked out from your purchase ledger with regulation 38's figures, and only the officer acting as section 151 officer or chief finance officer can approve it, with their job title. Payments over £30,000 are listed each quarter with regulation 38A's fields and frozen when published. The contract register works out each contract details notice and contract copy deadline, and tracks the key performance indicators for contracts over £5 million. Your council publishes each notice on the Central Digital Platform. Read the Transparency Code guide for the quarterly data.

Sources

This page follows the Act and the regulations as published on legislation.gov.uk and the Cabinet Office's guidance. It covers councils in England; procurement regulated by the Welsh Ministers has some different rules and dates. It is general guidance, not legal advice: for a decision on a procurement, ask your procurement or legal team.

Last reviewed 13 November 2026.